> SAMPLE RECORD — Example Harbor Hotel Owner, LLC is a fictional company. All names and figures are illustrative EXAMPLE DATA.

# Board Decision Record

**EH-2026-11** — Approve change-of-standards PIP spend of $2.4M (EXAMPLE DATA)

*Example Harbor Hotel Owner, LLC (SAMPLE — fictional) · Board of Managers*

- **Board:** Board of Managers
- **Organization:** Example Harbor Hotel Owner, LLC (SAMPLE — fictional)
- **Status:** CLOSED
- **Outcome:** APPROVED
- **Date:** Sep 17, 2026
- **Meeting:** Q3 board meeting
- **Moved by:** Renée Castillo (Chair)
- **Seconded by:** Tom Akers

## Rationale

Phasing keeps the work inside the off-season, uses the reserve as intended, and avoids a termination fee. The change-of-brand and sale options were reviewed in the alternatives memo and rejected on cost and timing. All figures are EXAMPLE DATA.

## Brief

- **Question:** Should the owner fund the brand's property improvement plan on the brand's schedule, negotiate a phased scope, or leave the brand?
- **Recommendation:** Approve the phased scope the brand agreed to in writing.
- **Options:** Fund the PIP, phased over two off-seasons (recommended); Fund the full PIP in one off-season; Change brand or go independent; Sell the hotel before the PIP deadline
- **Risks:** Cost overrun on corridor work (contingency carried as its own line); Rooms out of service longer than planned in the second off-season
- **Financial impact:** Up to $2.4M (EXAMPLE DATA): reserve balance funds part; members fund the rest by capital contribution. No new debt; lender consent obtained.

## Evidence reviewed (sealed pack)

- Brand PIP letter and line-item list — opened by 5 of 5 directors
- Third-party cost estimate with contingency line — opened by 5 of 5 directors
- Funding memo: reserve balance before and after, member contribution — opened by 5 of 5 directors
- Alternatives memo: phased vs. one-season vs. rebrand vs. sell — opened by 4 of 5 directors
- Brand's written agreement to the two-season phasing — opened by 5 of 5 directors

## Motion

RESOLVED, that the Board approves capital expenditure of up to $2.4M (EXAMPLE DATA) for the guestroom and corridor scope of the brand's property improvement plan, phased over two off-seasons as agreed in writing with the brand, funded from the FF&E reserve and a member capital contribution as set out in the capex memo (Pack item 5.1); any increase above 5% returns to the Board.

## Vote tally

Aye 4 · Nay 0 · Abstain 0 · Recused 1 · PASSED

## Recusal

- **Graham Whitlock** — A family member owns a casegoods supplier that submitted a bid. Disclosed in the annual questionnaire and again on this item; left the room for discussion and the vote.

## Actions

- Execute contractor agreement within approved budget · Nadia Brooks, asset manager · DONE · due Oct 3, 2026 · formally closed
- Add PIP cost and schedule lines to the monthly owner's KPI pack · Nadia Brooks, asset manager · DONE · due Oct 15, 2026 · formally closed

## Monitors

- 12-month check: cost, schedule, and results after phase one · ACTIVE · Actual cost vs. approved budget; RevPAR index vs. the pre-renovation baseline stated in the memo · target Cost within the approved budget; index at or above the baseline in the memo · due Oct 14, 2027

## Closure evidence

- **Evidence:** Executed general contractor agreement (signed October 2, 2026); Lender consent letter; Brand acknowledgment of the phased PIP schedule
- **Closed by:** Nadia Brooks, asset manager
- **Closed at:** Oct 8, 2026, 1:00 PM EDT

## Record context

- **Meeting:** Q3 board meeting
- **Meeting status:** Completed
- **Scheduled:** Sep 17, 2026
- **Agenda position:** 5
- **Quorum:** Quorum met — 5 of 5 directors present (met)
- **Pack:** Sealed
- **Pack SLA:** Met
- **Pack opens:** 5/5 opened
- **Minutes:** Approved

## Governance history

- **Sep 10, 2026, 4:00 PM EDT** — Pack sealed (7 days before meeting) · Board secretary
- **Sep 17, 2026, 11:20 AM EDT** — Recusal recorded · Graham Whitlock
- **Sep 17, 2026, 11:20 AM EDT** — Vote certified 4–0, 1 recused · Renée Castillo (Chair)
- **Oct 8, 2026, 1:00 PM EDT** — Closed with evidence · Nadia Brooks, asset manager

## Certification

This Decision Record summarizes the board record for **Board of Managers** as of **Sep 17, 2026**. It is a portable trust artifact (summary rows only; no document binaries or privileged notes). Credentials inside links (meeting passcodes, signed-file tokens) are redacted; host and path are kept.

---
*Generated by Prepared Board · Nov 10, 2026, 9:10 AM EST · Open the HTML export for Print → PDF.*